Hurricane Wilma Information
Thursday, October 27, 2005 - Note on why
lobby wall failed
The lobby walls on the bottom half were
papered with heavy vinyl wall paper when the lobby was remodeled. The lobby
walls are outside walls thus creating a vapor barrier. as the lobby is air
conditioned, the vinyl wallpaper creates condensation eventually soaking and
weakening the sheet rock. That is why the bottom half of the sheet rock blew
out during Wilma.
All this vinyl will have to be removed and the sheet rock replaced. It
should not have been installed this way.

Wednesday, October 26, 2005 - Afternoon
Update from Sandy Harwood
Well it is only Wednesday and only two days
after the hurricane and we are making progress! Service master
promises to have all the units dried out by Friday Night. R. L. James
is putting more men on the job with the objective to be complete by
Thanksgiving. Roof should be completed by next week. Air
Conditioners are being hooked up and should be complete by the end of next
week. The penthouses have had any openings in the floor Caulked!
Other news: Hotel is shutdown for three weeks, because of water intrusion
into the units through their new sliders.
Punta Rassa has major problems and they don't fund their reserves. So no
money and NO workers without money.
We are very fortunate that we have contractors on site. We have money and
the work is going full speed ahead.
Unit Inspection List
- Microsoft Word Format - click to open
Hurricane Day Pictures

Wednesday, October 26, 2005 - Morning Update
from Sandy Harwood
Update - Microsoft Word Format - click to open
An update from our contractor is coming
soon (delayed due to technical problems).
Individual unit inspections are being typed
and will be posted soon.

Monday, October 24, 2005 - Update from
Shannon Paolocci
I just heard
from Sandy. She went out to the building to check on damage. This is her
preliminary report, but the winds are still very high and they couldn't
look at everything. It is still dangerous to be outside.
The roof
looks good and the air conditioning units are ok.
The 37
storefront (unit 137) is damaged.
The lanai
screen enclosures on the 31 and 37 risers took a beating - will probably
have to be replaced.
The windows
are intact.
There is a
wall blown out in the lobby.
One of the
penthouses had some damage and water came in. There are some water
problems on the 35, 36, and 37 risers. Won't be able to get in and assess
how much until tomorrow.
The
contractor will be on site tomorrow. Sandy will be going back tomorrow to
go through each unit and assess any damage. I will report any news as I
get it. The power is out and they think it will be 2 or 3 days before it
is back on. She will send pictures when she is able.