Spalling/Concrete Restoration Project

July 25, 2005 Notice
We have been experiencing problems with contractors and
decorators hired to do work in individual units walking in areas where they
should not be. We must be very careful now that the critical phase of
the walkway work is beginning. During the tile floating,
waterproofing, and drying phase of the walkways, each floor will be blocked
to everyone, there is no admittance onto that floor for at least 3 weeks.
Once Mr. Bigos has determined that floor is capable of handling traffic, it
will be opened, and another one or two will be closed.
Any unauthorized entry onto a closed floor causing damage
will result in all contractors and decorators being banned from the building
until the work is complete. In addition, those causing the damage will be
charged for a full repair. This information will be posted in the
lobby and elevators as well.

July 19, 2005
Following
are the prices for having the lanai tile replaced through the concrete
restoration program. These amounts will be invoiced to those owners who
have agreed to have their tile done through us. Invoices will be
sent this week.
31
Riser $2,107.70
32, 33, 34, 35, 36 Risers $1,155.55
37 Riser $2,871.10

Go to
www.daltileproducts.com and click on the "Locate Us" link to find dealers in
your area to see the tile selections in person.
Tile Selection