Renovation Photos |
Renovation Project Budget
This phase of renovation has been
completed. Following the 1999 annual meeting, the Board of the Sanibel Harbour Tower South Condominium
Association reported its decision to pursue a course of action that would resolve the continuing
water intrusion problems affecting many of the units in the building. Since the condominium was
built in 1985, the Association has incurred excessive repair and maintenance costs due to water
penetrating from defective windows and cracks in the decorative columns. The action taken by the
Board was in conjunction with a building condition and evaluation study conducted by Welbro
Management, Inc., in August, 1999 and their subsequent recommendations regarding the scope of reconstruction.
Following the annual meeting, the Board voted to pursue a scope of work proposed by Welbro and authorized Moore & Spence Architects to prepare design drawings and specifications and
to select a qualified general contractor to perform the work. During this process, the Board also
consulted with a qualified roofing professional, to determine the condition of both the upper (12th floor)
roofing system as well as the flat roof covering the front entrance (portico).
Based upon the preliminary scope of work, the Board estimated the budget at approximately
$400,000 prior to any roof work.
Due to the tremendous construction activity in Southwest Florida, the number of construction
firms capable of executing this type of project is small and it proved difficult for our architect to
find qualified contractors to bid on such a complicated job. Starting with four contractors, Moore &
Spence ended the process with only two serious bidders for the work. In addition, due to the high
number of unknown factors in the scope of work, many of the costs were bid as estimates; the extent
of the total cost to be determined only upon completion of the project.
As a result of these factors, the preliminary budget increased
substantially and the total cost of the
project could not be fully determined until
the work was completed.
The Board considered funding the costs associated with the remedial effort with a two-year
assessment program that would include interim financing through a short-term bank loan. Prior to
finalizing its decision, a special Board meeting was held on September 28, 2000 to ratify the proposed
budget and assessment program. The Board delayed its final decision on this matter to allow time to
solicit any written comments from Association members.
Items included in the renovation project were as follows:
 | Portico Column Replacement - damaged as a result of continuing water intrusion from the flat (portico) roof.
|
 | Vertical and Horizontal Wall Fins and Arches (decorative wall columns) - many of these wall fins
are severely cracked and were poorly designed. The columns will be removed and patched with new stucco then
painted with an offsetting color from the rest of the building. |
 | Window Replacement - all window units on the north, south and west (Bayside) of the building
will be replaced with commercial grade, hurricane wind-rated windows. Many of these windows are currently
experiencing failure. All are expected to provide a source of water intrusion in the future if not replaced. |
 | Strip, Seal and Paint Building - damaged stucco to be repaired and the entire building primed
then sealed with one coat of 100% acrylic paint. |
 | General 12th Floor Roof and Soffit Repair - includes reattaching loose materials, repair of
roof drains, removal and replacement of all louvers and hatches and painting and sealing of air conditioner
platform posts. |
 | Portico Metal Roof - replacement of existing flat roof with a sloped metal roof system |
 | Architect/Engineering Services |
 | General Contractor overhead/fees |
 | Exterior Stucco Replacement |
 | Concrete Replacement |
 | Wall Partition (metal stud) Replacement |
 | Expansion Joint Replacement |
 | Window Stucco Repair |
 | Interior Drywall Repair (replacement) |
 | Corner Bead Replacement |
Although the full extent of the cost of the items outlined above
could not be fully determined at the time
the project started, Moore & Spence provided
the Board a range of costs to assist in
securing a source of funding for
the project. Therefore, at the September
28th meeting, the Board levied a special
assessment of $12,500.00 per unit. The
Special Assessment is payable in two installments.
The first installment was due and payable
October 31, 2000 in the amount of $5,000.00.
The second installment is due and payable
on September 28, 2001 in the amount of
$7,500.00.
Considerable time and effort was spent working with a team of professionals
to plan the most appropriate course of
action and permanently resolve the ongoing
water damage. The Board members realized
the value of the owner's investment in
the building increased substantially
in the past few years and realized that
everyone wanted to preserve their assets
well into the future.
The members of the Board collectively agreed to resolve these
issues as comprehensively as possible while
cognizant of the burden a special assessment
would bring to the owners. Through the
consultants, the Board "valued engineered" the project without sacrificing
a long-term, permanent solution.
The existing painting and roof replacement reserve was utilized to
subsidize the initial assessment while
the interim loan allowed the owners
the ability to spread the cost over a two-year
period.