Home
Calendar
Condo Board
Management
Parking Permit
Newsletters
Owner Updates
Maintenance
Security
Insurance
Specifications
History
Contact Us
Links
FAQ's
Search
Archives

   

Hurricane Charley Roof Construction Project

December 19, 2005 Update

This report mainly covers the work that is taking place to complete the main project. First I contacted Lightning Protection Systems this morning so they can schedule their people to finis grounding the aluminum A/C stands, the aluminum stairs and guards and any other miscellaneous items. The final copings are in place and the roof surface has been cleaned up of debris.

Last week Tom B. and I decided to try to install one of the new Trash Room Access Doors. We spent about 1/2 hour cutting two wedges to use and commandeered Rob Davis and a helper from RLJ. The old door came out in less than 5 minutes. The first new door took about two hours because we didn't quite know what we were doing, so the holes were pre-drilled prior to attaching the screws. From there it went real quick and at the end of the second day, the doors were in, the perimeter openings caulked and the trim panels installed. They look good and work good.

The 37 riser screen enclosures have been installed and Creative Tile has been notified regarding the tile install at 437, 537, 737 and 837. All of the interior lanais are complete as to tile and grout. Any lanais to receive sealant will be completed with the remaining tiled decks. RLJ is taking delivery of the 31 enclosures this week and will be installing them as they arrive. The screening people have arrived back to the property this morning to continue their work. Maybe they'll catch up to the enclosure install, so long as they don't step onto wet tile. All of the walkway base is on site and is being installed.

Regarding the electrical problem with 237, it was originally surmised that RLJ nicked the conduit from 337 during the excavation of the deck. However, we found that there are at least two areas that have shorted out, one on the west side which has been repaired and new wire pulled between the two ceiling outlets. The second short is knotted up between the north outlet and the main switch located in the Master Bedroom. From the ceiling box, the conduit travels up into the center of the slab and then turns on the diagonal to the switch. It has been a real pain to watch the contractor cut the concrete and hammer it out overhead right after the lanai was cleaned. The good news is the electrician will be here Tuesday morning at 8:30 AM to make the repair and RLJ can pack the overhead repairs with a very plastic repair mortar called Gel Patch.

To answer any questions regarding the 31 riser, RLJ will be working the week between Christmas and New Year's.

Have a Merry Christmas and a Happy New Year!

Joe

Picture Gallery - Click on the left or right arrows to page through the gallery. Click on the specific picture to enlarge it below.

.


 

   

©2001 Sanibel Harbour Tower South Condominium Association, Inc.
Privacy Policy | Feedback Form