Home
Calendar
Condo Board
Management
Parking Permit
Newsletters
Owner Updates
Maintenance
Security
Insurance
Specifications
History
Contact Us
Links
FAQ's
Search
Archives

   

Hurricane Charley Roof Construction Project

November 4, 2005 Update

Good evening to all: It seems things are starting to wind down a little. West Coast Roofing as of Friday last was working on the last of the metal panels at the north side of the north A/C Pod. This past weekend they Marteen and his crew were going to be setting the ridge flashing on the north side. They can't finish the under window flashing at the penthouse clerestory windows until the windows are installed, however I asked them to caulk seal along the sill interface until that time. The lower flat deck is complete with the exception of the metal cap. The upper curbs have been poured and covered with roofing membrane and await metal. The upper stair to the elevator is in and the 14th floor walkway rails are ready for install later this coming week as soon as the hoisting equipment is removed.

Mabry has completed charging the north pod and had started the 34 riser pod on Friday. This week he hopes to have some additional help on the south pod as it takes quite a long time for one person to do it. I watched him and you can see the humidity slowly bleed from the vacuum pump. They half to suck out all of the moisture from the first floor to the 14th floor.

I will be inspecting the 31 riser with John Z. Monday morning prior to commencement of the pour-back of those decks. quantities will be taken along with photos of each repair for the photo album. Complete Aluminum is starting to install the screen enclosure for PH-1 which came in this past week. Both exterior penthouse decks have been waterproofed. The 32 and 33 risers are being tiled and the other interior lanai risers are finished with the exception of some tile repairs. One word of caution, the 31 and 37 risers cannot be tiled and the mast climbers will not be removed until the screen enclosures are replaced. Complete Aluminum has been put on notice to measure those lanais and commence fabrication.

The new compactor showed up on property this past week and a portion of the trash room slab needs to be raised around the floor drain to provide adequate support for all wheels.

In closing, the roofing project is on schedule for completion this week and it appears with the exception of the windows, the restoration project may be completed a day or two ahead of their schedule.

Picture Gallery - Click on the left or right arrows to page through the gallery. Click on the specific picture to enlarge it below.

.


 

   

©2001 Sanibel Harbour Tower South Condominium Association, Inc.
Privacy Policy | Feedback Form