Home
Calendar
Condo Board
Management
Parking Permit
Newsletters
Owner Updates
Maintenance
Security
Insurance
Specifications
History
Contact Us
Links
FAQ's
Search
Archives

   

Hurricane Charley Roof Construction Project

September 29, 2005 Update

The most important item that has taken place this week is the commencement of the work on the air conditioning condensers. New copper tubing, insulation and thermostat wiring has started with the 35 riser. The group of line sets located at the far north end of the roof had to be cut off inside the attic space and modified to fit into a gooseneck pattern so a code required hood could be attached over the assembly. As you can see by the photos, the lines are being laid out to their appropriate location (the equipment platforms have been marked with corresponding apartment numbers.

The roof protection curbs have been poured at both the lower and upper equipment decks. The second mechanical stair will be installed the first part of this week.

The roof panels are being installed at the south side of the building. The exception is the inside face of the North Stair Tower and the North end of PH-2 (this area is waiting for stucco to the chimney box and the inside face of the stair will more than likely be the last area roofed).

RLJ is grinding the 31 riser and 37 riser and there is a lot of concrete dust in the air. The 32 and 33 risers are being excavated. We found some additional damage at the ceiling of 437. What was to be only stucco repair ended in a large overhead spall with corroded conduit. The third floor is almost complete (re-tile due to color issues) and then the tile contractor will be sent to the seventh floor to replace all of the cut tile perimeter pieces (these are also the different color). The 12th floor has been repaired and sloped and is awaiting the completion of the roofers and A/C people. Once this floor is tiled, then the walkways can be cleaned and touched up and re-painted.

It is my understanding, John Z has given direction to the tile company to finish the walkway base work before moving onto additional lanais.

The pool cover has been taken down and removed so Tom B. can start his clean-up.

One final note, even though the contract between West Coast Roofing & Waterproofing is winding down, R.L. James is still working and is still in control of the building. Both contractors are responsible for their own clean-up of the premises as defined by the Specifications and Contract. It is premature to commence cleaning now as it will only get dirty and dusty again. The walkways have been washed down twice, once from the inside and once from the mast climbers, however they are dirty again and will remain so until the end of the project.

Hopefully I will have information on the windows this week as it has been to weeks plus since the shops were approved. I tried contacting the project manager direct on Friday and got her voice mail and left a message to call me back. I guess everything as far as ordering, etc. has to go through KNZ, PA .
Joe

Picture Gallery - Click on the left or right arrows to page through the gallery. Click on the specific picture to enlarge it below.

.


 

   

©2001 Sanibel Harbour Tower South Condominium Association, Inc.
Privacy Policy | Feedback Form