Home
Calendar
Condo Board
Management
Parking Permit
Newsletters
Owner Updates
Maintenance
Security
Insurance
Specifications
History
Contact Us
Links
FAQ's
Search
Archives

   

Hurricane Charley Roof Construction Project

September 26, 2005 Update

Good Morning (afternoon): Sorry about this report being a little late as we encountered a couple of rain days early last week (Rita) that affected the work progress on the metal roof. West Coast is busy on the south side of the upper roofs with emphasis on the waterside. They are starting to fabricate and install the final flashings along panel termination locations. The second new stair up to the Elevator Equipment Room is due to arrive this week and be installed. Also had the contractor replace the old access panels with louvered ones with insect screen to provide some natural ventilation inside the enclosed attic space.

Good News! I met with one of the air conditioning techs from Mabry Friday and they have started. This week there should be three crews working on the equipment set-up and electrical connections. I requested they start on the 35 riser with emphasis on 935.

There are only two mast climber left on the building - one for the 31 riser and 1 for the 32/33 riser. RLJ is completing their pours on the 37 riser, are grinding the slabs at the 33/32 risers and removing tile from the 31 riser. Creative Tile has sent a man out to handle the re-tile of the 3rd floor walkway. Speaking of which, you all know why manufacturers ask that tiles be pulled from different boxes during installation in case there is a color or pattern variation from lot to lot. In most cases the color range is similar enough the difference in color variation is slight. However, on the third floor, the color change was so great, a new color could have been introduced ("Red Smoke"). It looked so blotchy, I wasn't impressed, especially coming off the elevator, so the floor was rejected.

There should be quite a bit of progress on the roof this week as West Coast's internal due date is set for the 15th of October.

Joe

Picture Gallery - Click on the left or right arrows to page through the gallery. Click on the specific picture to enlarge it below.

.


 

   

©2001 Sanibel Harbour Tower South Condominium Association, Inc.
Privacy Policy | Feedback Form