Home
Calendar
Condo Board
Management
Parking Permit
Newsletters
Owner Updates
Maintenance
Security
Insurance
Specifications
History
Contact Us
Links
FAQ's
Search
Archives

   

Hurricane Charley Roof Construction Project

September 2, 2005 Update

We were blessed by the passing of Katrina, however not so for our friends, relatives and fellow Americans along the Gulf Coast.

1. West Coast roofing is planning to have the crane dismantled and moved from the property Saturday morning (9-3-05).
2. They are installing metal panels along the North mansard roof. The 12th floor mechanical stair has been installed.
3. Finish work is continuing on the upper mechanical roof decks in torching down the final granular cap sheets to the vertical parapet walls and
structure walls prior to installation of the metal flashings and copings.
4. The A/C equipment stands on the upper mechanical decks have been installed and the circular "pitch pans" have been or are in progress of being installed. The "pitch pans" today consist of a pre-fab two-piece plastic ring set on the deck and sealed with a urethane sealant. The center of the ring is filled with a two-part polyurethane sealant. This is the third line of defense in prevention of water intrusion into the roofing assembly.
5. Avis Plumbing is installing two new roof drains to replace the" jury-rigged contraptions" used in the last roof project. The old drain consisted of a rubber ring with a lead pipe boot shoved into a 4" diameter PVC pipe. This pipe was then butted against a 4" to 6" expansion fitting.  The lead boot was crimped down at the end causing the roof water to back up and drain into the overflow drain or the nearest cut down sanitary vent.  Both of the upper roof drains are being replaced. The lower mechanical roof deck drain doesn't appear to have the problem, however this drain was re-fitted with a retro-fit drain.
6. Avis is also manifolding a number of vent stacks together in the penthouses to provide a limited number of penetrations through the metal roof panels. The location of the penetrations is coordinated with Marteen, the metal roof installation foreman. By the end of next week, Avis Plumbing should be finished with their roof work.
7. West Coast had scheduled Mabry out this past week to clean and move the condensing units to the roof, however with all the roof panels and other equipment, parts and components on the roofs, Mabry could not get the equipment onto the rails. Therefore next week when the flat roofers are finished, Otey will get Mabry back out to get the equipment mounted to the rails.
8. Earlier this week a swing stage was set up to replace the soffit and fascia along the front side of the Elevator Tower. Next week H & E will come out and add three more sections to the two mast climbers so the last 10 feet of the North and South soffits can be completed. When finished, these two climbers can be moved to the Southside of the 31 riser for soffit and fascia work. The aircraft warning light is up and running, however we will have to hold it steady using stainless steel guy wires anchored to the Elevator Tower roof eave. This will be completed prior to moving of the climbers.
9. RLJ has completed risers 36, 35 and 34 and is removing tile from the 33 and 32 risers. The 37 riser is still in the removal stage with some additional damage running under 1037's wood flooring. As of end of business today, we had not heard anything from Creative Tile for a proposal to replace the flooring or permission from the owner to remove the existing flooring to make the repairs. They've been informed through Benson's, but have not given written authorization. I will wait unit this coming Thursday and if I don't hear anything from Barbara, I will give authorization to John Z. to proceed with cutting select portions of the floor out. By the way, the floor is buckled above the spalls inside the unit and the sliding doors have been removed with temp walls built. 
10. Walkway floors 11 to 2 have been waterproofed and tile is being set in various stages on floors 7, 6, 5, 4 and 3. Sealants have been installed on 11, 10, 9, 8 and 7, however some additional work needs to be performed an all floors except 11.

Next week will bring a new set of photos and more to show.

Joe

Picture Gallery - Click on the left or right arrows to page through the gallery. Click on the specific picture to enlarge it below.

.


 

   

©2001 Sanibel Harbour Tower South Condominium Association, Inc.
Privacy Policy | Feedback Form