Home
Calendar
Condo Board
Management
Parking Permit
Newsletters
Owner Updates
Maintenance
Security
Insurance
Specifications
History
Contact Us
Links
FAQ's
Search
Archives

   

Hurricane Charley Roof Construction Project

August 9, 2005 Update

The following observations and comments on the project are as follows:

1. The sloped roof is proceeding with the installation of the metal panels at the upper sloped roof of PH-1. The spacing of the clips is approximately 12" on center

2. Soffit installation continuing along 12th floor at PH-2 and along north side of building.

3. West Coast ordered two additional mast climbers to be installed along front of building for soffit and mansard roof replacement in addition to the three at the waterside and one at the 37 riser. We may have discovered how the street side bedroom window walls continue to retain moisture during and after a rain storm. The installers from H & E Hi-Lift found that as they were tightening the anchor bolts for their equipment against the building on the street side, the stucco behind the anchor plate was bowing inward and cracking. Upon further exploration, we found a vertical gap between the outside face of slab and backside of the gypsum sheathing of approximately 2 inches. A similar condition occurs at PH-1 except the gap is 3 to 4 inches. The building was not plumb and square when built, so the solidly to the concrete slab. The affected openings will be filled with expanding foam and at the completion of the work, measures will be taken to ensure a weather tight stucco seal be made.

4. RLJ has waterproofed down to the 6th floor, tiling on the 8th and 9th floors and commencing waterproofing of the 36 riser. Tile demolition has commenced on the 37 riser. They just took delivery of the Silver Smoke color packs for the expansion joint sealant and will commence joint sealant application once the tile setters are completed with the floor grouting down through 9.


5. The sliders have been removed from PH-2 and the temp wall installed with an access door. The soffit along this lanai has bee re-framed using an 8" wide hat channel to support the head of the new screen enclosure.


6. I took receipt of the window and door shop drawings mid week and returned them to RLJ Friday afternoon, "Rejected, Revise and Re-submit." KNZ missed the sliding glass penthouse doors and detailed the wrong windows. They are in possession of them as I speak and I expect to see a revision by the end of the this week.


7. The aluminum A/C stands have arrived and West Coast will be fabricating a sub-frame to be installed to support the trunk line electrical feeds from the disconnect boxes.

8. Met with the plumber to discuss a number of issues discovered with the project.
A. 12th Floor Overflow Scupper: This scupper was install under original construction, however the finished end in the soffit was made of flexible dryer vent. We will re-locate it closer to PH-2 to exit the soffit near 1134 Bedroom window. The main roof drain at the 12th floor roof deck has an additional overflow drain near the main drain.
B. The biggest problem is the leak in the Laundry Room of PH-1 from the roof drain on the upper mechanical deck above this room. This drain was never seated properly and the pipe extension through the roof slab had been cut down to fit the drain hub. This connection will be cut off and re-worked with the drain hub and sealed from the underside.
C. As the new roof panels are 16" wide, a number of the existing vents may interfere with the panel seams. The largest diameter pipe on a given roof will govern the pattern of the panels for that area. All other pipes that penetrate the roof will be gathered into one 8" diameter vent and exit out horizontally to the nearest gable wall at a pitch of 1/8" per foot. This will eliminate the number of vertical penetrations through the vertical roof system.

9. Discussed with Jerry Goodhew, the new overseer from West Coast, the flashing of the short walls under the clerestory windows at both penthouses, 1131 and 1137. We will be disposing of the stucco under these windows and replacing with pre-finished flashing material.

There will be a contractors meeting this coming Thursday at 9:00 AM at the property to discuss the state of the project and any open questions. I asked Jerry to contact Lightning Protection Systems, Inc. to prepare them for their portion of the work.

Joe

Picture Gallery - Click on the left or right arrows to page through the gallery. Click on the specific picture to enlarge it below.

.


 

   

©2001 Sanibel Harbour Tower South Condominium Association, Inc.
Privacy Policy | Feedback Form