Home
Calendar
Condo Board
Management
Parking Permit
Newsletters
Owner Updates
Maintenance
Security
Insurance
Specifications
History
Contact Us
Links
FAQ's
Search
Archives

   

Hurricane Charley Roof Construction Project

July 31, 2005 Update

This report is being written on the 31st of July, however it pertains to activities from the 27th and 28th.

I will start with R. l. James first. Walkways 9 and 10 have been sloped and waterproofed. Another tile crew will be on site Monday morning to start tiling one of those floors. The first tile crew worked Saturday to finish tiling the 11th floor, will grout the floor on Monday and move to the other waterproofed deck. Thursday afternoon John Z. and I inspected the remaining walkway floors for crack chasing and concrete repair items. These are now ready for final repairs, surface preparation and waterproofing. Bob James, owner of R. L. James, Inc. was at the meeting and after looking at the 11th floor commented on how good the floor looked. He said it was "awesome looking".

There was a project meeting Thursday morning with the majority of discussion centered around the coordination of use or lack of between the two contractors. It appears the north climber will be moved this coming week to the 37 riser to commence tile removal. Monday, John and I should be able to perform the pre-pour inspection and quantity take-off on the 34 riser. To date, all exterior mounted shutters have been removed from both penthouses and the screen enclosure for Penthouse 2. Penthouse 1 is starting to remove their tile and as yet do have permission to remove their sliding glass doors.

Regarding the windows, John Dahin has sent out a contract to KNZ for windows and install and has received the signed version back. I should be receiving the window and shop drawings via FedEx Monday to begin review and processing. As I will be out of town a week from Monday, this submittal will be turned around this week. I've been told by a number of individuals at RL's office that the window is still open for the delivery and installation to coincide with the restoration contract.

Now to West Coast Roofing. I was informed Friday to contact Service Painting to schedule themselves to finish prepping and painting the gable walls of the two penthouses. If you recall, we held out some money from their last payment application to come back and finish painting those walls and West Coast doesn't want them on the new roof panels. West Coast had some problems with the high reach from Sun Belt so they ordered a slightly larger piece of equipment from another equipment rental company. Both upper flat roof decks have been stripped and covered with the torch-down smooth surfaced base sheet. You can observe quite a bit of corroded conduit penetrating the existing slab surface. As the contractor began to remove the roofing at the lower mechanical deck, they found this deck to have the original light-weight insulating concrete. I observed the condition of it with Scott Otey VP and everyone agreed that since there was no evidence of water intrusion into the concrete, we would use it as a base for the new roof system. There will be a deduct change order for not removing the deck sub-strate in this area. There is slope on the deck and some modifying would be required at the roof drain to lower the drain about 2 inches. We uncovered an overflow scupper that had bee covered over some time ago - this we will have Avis Plumbing rework to empty out through the soffit.

The procedure shown in the photos includes stripping the old membrane off the lightweight concrete. The concrete is then cleaned off of debris and dust and chalk lines are set as guides for the sheets of Dens Deck Prime (the gypsum-based based green finished sheet for the new roof system). The Dens Deck is attached using a two part structural foam adhesive. It comes out of the mixing nozzle as a yellow liquid and within 30 seconds starts to expand. The Dens Deck is placed over the adhesive and pressed lightly. In five minutes it is set and men are walking on it. Following completion of an area, approximately one quarter of the deck, the smooth surface base sheet is torched on and up the wall about 12 inches and the roof is watertight. We did find out that the rectangular box on the lower roof deck is a solid reinforced concrete pad probably for future mechanical equipment and the other smaller pads are for supplementary support of the penthouse sun decks to keep those decks off the roof membrane.

West Coast and I met with Jim Mabry from Mabry Brothers Mechanical to discuss the repairs to the electrical feeds through the slabs and the lightweight. From what he observed, and he will have one of his electricians come out Monday morning to confirm his belief, we may be able to abandon the existing conduit and wiring in the slabs and run new flexible plastic conduit from the wall-mounted disconnects and along the new support rails for the condensing units. This would keep the mechanical decks cleaner and minimize the number of penetrations in the roofing membranes.

One item West Coast did say regarding the new roof panels, that when the seaming machine comes out to run the 180 degree double lap seam, due to the overall thickness of the aluminum sheets and the clips, the finished look along the seams will be a little wavy.

Finally, West Coast is providing daily clean-up of nails, fasteners and screws that have fallen onto the grass areas and driveways. Early Friday they came out and covered the pool with Styrofoam blocks, 2x4s, plywood and plastic. It is definitely off-limits to everybody until their work is completed. However, Tom has an area he can lift up to check the pool chemistry and add chlorine.

Joe

Picture Gallery - Click on the left or right arrows to page through the gallery. Click on the specific picture to enlarge it below.

.


 

   

©2001 Sanibel Harbour Tower South Condominium Association, Inc.
Privacy Policy | Feedback Form