Home
Calendar
Condo Board
Management
Parking Permit
Newsletters
Owner Updates
Maintenance
Security
Insurance
Specifications
History
Contact Us
Links
FAQ's
Search
Archives

   

Hurricane Charley Roof Construction Project

July 20, 2005 Update

Good morning: Yesterday was an exciting day at the project site. RLJ is starting to prepare walkways 11 and 10 for sloping. This includes a water test of the surfaces and allow to dry for a minimum of 4 hours to see where the water ponds. The largest area is in front of the elevators, in front of the 31 and 37 entry doors. Unfortunately, all we will be able to do is relocate the water to another location. The surface prep work consists of roughening up the surface and channeling the slab at the low end to receive the sloping material which will be toweled on in lifts of 1/8" to 1/4". Anything thicker will mud crack. If all goes well, the contractor will be waterproofing those two decks on Monday or Tuesday followed by the tile setters. Those two floors will be off limits to all other contractors and resort personnel until the sealants are complete and cured (approximately 2-1/2 weeks per floor).

West Coast is stuccoing the South gable wall at PH!, is completing the sub fascia work there and getting ready to install the finish fascia and soffit at that penthouse. I have not heard one word from Maureen regarding her exterior mounted shutters and their removal, however, by early next week she will be holding the progress of the work up. It was my understanding she was to be in town this week, however Tom B. informed me she flew in and out last Thursday. Unless the board or management can explain to her the importance of removing the shutters to put on the soffit, I will direct RLJ to do so and put them inside her unit. PH2 has authorized R.L to remove their shutters and toss them out.

Back to West Coast Roofing - they have installed the soffit along the underside of the elevator tower (area that is reachable by scaffolding). They have installed roof panels along the river side mansard. There are seven-6" clips per panel and each clip is screwed to the deck with two corrosion-resistant wafer head phillips head screws. Once the panels are secure, there will be three corrosion-resistant screws per panel screwed along the eave edge up 3" for uplift resistance. All this is in accordance with the engineered shop drawings prepared by the panel manufacturer and their specialty engineer. Finally, a machine will mechanically seam the panels and clips to form a double 180 degree seam.

Finally, in my walking of the floors, I've noticed quite a few owners are updating their units and performing interior re-paints. As a reminder, all interior remodeling over $750.00 requires a building permit and R.L. James is not the general contractor for that work.

Last, I'm waiting for the window shop drawings from Traco - the windows were re-measured last Thursday.

Joe

Picture Gallery - Click on the left or right arrows to page through the gallery. Click on the specific picture to enlarge it below.

.


 

   

©2001 Sanibel Harbour Tower South Condominium Association, Inc.
Privacy Policy | Feedback Form