Home
Calendar
Condo Board
Management
Parking Permit
Newsletters
Owner Updates
Maintenance
Security
Insurance
Specifications
History
Contact Us
Links
FAQ's
Search
Archives

   

Hurricane Charley Roof Construction Project

July 11, 2005 Update

To start, the crane was lowered to the ground last Friday due to Hurricane Dennis. West Coast Roofing work in the morning to tie everything down on the roof. Four scaffolding planks still broke free, but did not fall off the roof. Instead, a lot of nails and screws did. One port-a-Jon fell over and the aluminum stair to the trailer wound up wrapped around a palm tree breaking the railing. They also installed the gable wall with exterior sheathing that fell in during Charlie. Today they worked on the lower sloped roofs at 1031 (south), PH-1 (south) and 1031 (east upper). I was able to get a couple of pictures from the resort stair tower looking towards the south side of our building.

The fascia that had been installed earlier at the penthouses was unacceptable to me and I sent an email to Scott Otey so stating. Apparently it was unacceptable to Tim Waters, their floating supervisor, who told the lead man on site to remove it. It didn't line up correctly along the finished backside and was oil-caning along the front side. It will be re-done to everyone's satisfaction. The J-mold was delivered to the roof along with additional sub-fascia and soffit. I happened to watch Anco Roofing roll out the metal roof panels for the north tower and they do look good - much cleaner than the panels that came off the building.

RLJ has started washing down the walkways following their application of sealants along the building face parallel to the front entry doors and along the door thresholds. When I left property this afternoon Oscar was on the 10th floor and was moving to the 9th. The next step is to clean-up the remaining walkway spalls and exposed bars (there are exposed atrium beam hoops exposed on the 8th floor that the contractor needs to address somehow.) I have requested a CO Proposal from RLJ to drill and fill all walkway rail post bases with epoxy to prevent the build-up of condensation and moisture in the bases below the finish surface of the deck. I have observed at least 4 to 5 rail bases that have spalled out following removal of the tile.

The lanais are progressing with repairs mainly to surface spalls due to reinforcement running at or above the surface of the deck. In most cases, the carrier bars can be lowered to accommodate the top steel to be lowered also. The 35 riser has two sliders that needed to come out - 435 Living room and 1035 Bedroom. The 36 riser has four sliders that came out - 636 Bedroom, 836 Edge-mounted, 936 Living room and 1136 Bedroom. Tuesday morning we will be inspecting the 34 riser and taking quantity measurements prior to pour-back.

In other matters associated with the project, I'm coordinating the design and construction of the fireplace chimney for 1232, communications with both penthouse owners regarding the removal of the storm shutters prior to the installation of the metal soffit (which is to finally begin next week and dependent on RL's pour schedule). Final measurement of the windows is to take place later this week by KNZ so that shop drawings and engineering can be prepared, submitted and reviewed.

Note: a number of photos will be from last week prior to the storm. The first photo is of one of the bee swarms. They both left after one day - they must  have been passing through. The remaining photos are of PH 2.

Picture Gallery - Click on the left or right arrows to page through the gallery. Click on the specific picture to enlarge it below.

.


 

   

©2001 Sanibel Harbour Tower South Condominium Association, Inc.
Privacy Policy | Feedback Form