Home
Calendar
Condo Board
Management
Parking Permit
Newsletters
Owner Updates
Maintenance
Security
Insurance
Specifications
History
Contact Us
Links
FAQ's
Search
Archives

   

Hurricane Charley Roof Construction Project

June 23, 2005 Update

Yesterday morning we received the first of many deliveries of tile for the building, one pallet of Kerelastic liquid, one pallet of Kerabond mortar dry mix and 1,600 square feet of walkway tile. All material is stored under the building.

West Coast has removed the connecting stair between the lower and upper equipment decks and has taken delivery of the scaffolding that will be built up to the underside of the elevator tower for soffit replacement. There will be a stairway attached. West Coast is working on the North side of 1232 on the lower roof, however it has been difficult with all the rain we're getting early afternoon. Yesterday it poured from 11:15 to 12:30, moved east and then drifted back to the coast. We're supposed to have 40% chance through the weekend into next week. The soffit install will commence early next week.

RLJ is grinding the 9th and 8th floors. A serious attempt was made to water scarify the floors, however the residue turned into concrete paste and splattered everywhere so this process was terminated. Hilti will be on site this coming Tuesday at 8 AM to demonstrate a new piece of equipment for grinding the floors. If it works out, RLJ will probably invest in a piece of equipment. The rains yesterday washed all the concrete dust from the building.

A crew is working on the 36 - 35 risers on concrete demolition. There aren't too many surprises on these deck - similar to what was discovered on 132 - mainly bar running on the surface. With the demand high by both contractors for the mast climbers, my inspections of the lanais will take place during the lunch hour as we do not want to hold anyone up in their work.

If Barbara can get me an email address for 1231, I can talk to them about upper level shutter removal. All exterior mounted window shutters have to be removed prior to installation of the new soffit, so there is continuity in the finish materials.

Photo 4 shows materials and tools left by Mabry. Tom B. and I have talked about the roofing contractor leaving power tools and boxes of screws, etc. in the penthouses. I spoke to Tim Waters about this and let him know the penthouses belong to individual owners and are off limits to the workers. If we find tools in those units, we will take possession.

This question is for Scott Otey - I'm requesting you have additional supervision on the project as there are times I have questions and Tim is at another job and I don't speak Spanish. Who is running the job in the field and how available is that person to give me daily progress reports and rain outs?

Joe

Picture Gallery - Click on the left or right arrows to page through the gallery. Click on the specific picture to enlarge it below.

.


 

   

©2001 Sanibel Harbour Tower South Condominium Association, Inc.
Privacy Policy | Feedback Form