Hurricane Charley Roof Construction Project

June 15, 2005 Update

There wasn't much to report yesterday except Mabry and the crane operator were not on site. The mast climber people were still setting up additional climbers - there are four on the North side.

All of the condensing units are down, cataloged and under the building in there own pods. West Coast is working on the waterside of Penthouse 1 as far as the climber will reach.

RLJ is down to the fifth floor on tile removal and will have both their large dumpsters replaced on Friday. They will be water grinding the 12th floor and washing the slurry debris down as they go to get rid of the dust.

We met this morning with Traco to discuss window types and may go to a out-swing casement for ease of cleaning - they do cost more, however they do provide a better seal along the window frame against water infiltration. John Dahin was meeting with the Traco rep this afternoon to discuss further.

We have 45 units that have signed up for the tile and we selected the grout for each color and passed them on to Creative Tile. Greg Goggins told me this morning that he has or is in process of revising his labor cost and material cost down due to the number of units to be completed in the project.

This week everything is under control and next week I start inspecting lanais for spalling.

 